Using Task Groups in Resource Planning

Task groups in Resource Planning — called Project Planning in BusyBusy — allow you to organize related tasks into a single phase of work.

Task groups make project plans easier to understand, manage, and adjust by grouping multiple tasks that belong together, such as site prep, foundation work, or framing.

When to Use Task Groups

Use task groups when you want to:

  • Organize multiple related tasks under a single phase.

  • Plan work that happens in a specific sequence.

  • Move an entire phase of work at once on the timeline.

  • Reuse common phases across projects.

Task groups are especially helpful for larger or more complex projects.

Create a Task Group

To create a task group:

  1. Go to Scheduling → Project Planning

  2. Open the project plan you want to edit

  3. Click the Hierarchy Icon under the project name

  4. Select New Task Group

  5. Enter a Task Group Name

  6. Choose a Start Date for the Task Group

  7. Add Tasks to the Task Group

  8. Click Create

The task group will appear in the project plan with its tasks listed underneath.

Add Tasks to a Task Group

Tasks inside a task group represent individual pieces of work within that phase.

When adding tasks to a task group, you can:

  • Select tasks that already exist as templates

  • Create new tasks directly within the task group

  • Define the Start Day offset for each task

  • Set the Expected Duration for each task

How Task Group Timing Works

Task group timing is based on the task group start date. The start day offset determines how many days after the task group start date a task begins.

  • Tasks with no Start Day offset begin on the task group start date

  • Tasks with a Start Day offset begin that many days after the group starts

  • Task durations determine how long each task appears on the timeline

This allows you to plan sequential work without manually calculating calendar dates.

Move and Adjust Task Groups

Task groups make it easy to adjust schedules when plans change.

You can:

  • Drag a task group on the timeline to shift all tasks together

  • Adjust individual tasks within a task group if needed

  • Edit task durations or start day offsets

Moving a task group automatically updates all subtasks while keeping their relative timing intact.

Save a Task Group as a Template

If a task group represents a phase your team uses regularly, you can save it as a template.

Saving a task group as a template allows you to:

  • Reuse the entire phase in future project plans

  • Retain task order, durations, and offsets

  • Standardize how work is planned across projects

Important Things to Know

  • Task groups do not schedule work on their own.

  • Tasks inside a task group can still be edited individually.

  • Task groups can include both templated and non-templated tasks.

  • Changes to templates do not affect existing project plans.